Three different inspections people call by one name
The city inspection belongs to the permit. San Diego's Information Bulletin 301 prices PV by first system or inverter plan check and inspection, and Visalia's FY 2026-27 schedule prints a plan check of $150.00 and an inspection of $300.00 for residential PV from 1 to 15 kW. The utility step is separate: PG&E, SCE and SDG&E give permission to operate after their review under Rule 21. A private inspection is the third kind, which you order yourself and which the model prices as a visit.
For a private visit, the scope is whatever you and the inspector agree, so ask for a written list of what the visit covers and what the report will say before you book it.
A private inspection's price in California, beside the city's own
Our model puts a private inspection at $165 to $355 per inspection visit. It starts from two national ranges and applies California's installer wage ratio of 1.09, adds no permit fee and takes off no federal credit. It's an estimate and not a quote.
The range doesn't cover repairs, a thermal scan, a report for a lender or a re-inspection. City rows in the table show what a city charges for its permit inspection, which is a different visit.
| Item | Figure | What it is |
|---|---|---|
| Estimated range, not a quote | $165 to $355 per inspection visit | Built from 2 national published ranges, adjusted by the California solar installer wage ratio (1.09). Before any incentive: there is no federal credit for a system installed in 2026. Basis: no California company price for this job, so the national estimate stands. |
| Solar photovoltaic installer wage, California mean | $30.42 an hour | Installer pay from BLS OEWS (May 2025); an inspection quote is priced separately. |
| PV residential 1 to 15 kW, inspection, Visalia | $300.00 (plan check $150.00) | FY 2026-27 schedule effective 2026-07-01. The city's permit inspection, not a private one. |
| PV first system/inverter inspection, San Diego | $275.80 | Information Bulletin 301, undated web page. The city's permit inspection, not a private one. |
| Solar PV, 10 kW or less, electrical permit and inspection, San Francisco | $283 | DBI Fee Table 1A-E for permits issued on or after September 1, 2025. The city's permit inspection, not a private one. |
Estimated range. Built from national published ranges (2 sources), adjusted by California's solar installer wage ratio to the US (1.09, BLS May 2025), plus the city solar permit fee where the city publishes one. Not a quote. One California installer publishes its own quoted range (per watt and per battery), too few to build a range from; the others print blog averages, which we do not count. We have no California company price for this job, so the range is our national estimate alone. Full method. Prices as of Oct 23, 2026.
What the city's own inspection covers, by city
Cities print what their permit inspection includes. Long Beach's IB-023 says its express permit fees cover all required inspection services, and Simi Valley's photovoltaic page lists a $25 administrative fee per project and says one inspection is included. San Francisco's DBI table for permits issued on or after September 1, 2025 prices the electrical permit and inspection for a system of 10 kW or less at $283. Each additional 10 kW is $238 (the row notes up to two inspections), and DBI may revise the table on July 1.
Oakland's FY 2025-26 schedule prints $450 for the residential solar electric inspection. In Thousand Oaks, SolarAPP+ approval isn't a permit until fees are paid and the city issues it. Ask your building department for the permit record and the final inspection date.
What the city inspector looks at on the day
Long Beach says its inspector checks the system against the PV checklist, the approved construction plans and the code. The construction documents, permit and job inspection card have to be on site, the inspector needs access to every part of the system, and ladders must be OSHA compliant. Approval comes "upon final inspection."
San Jose's inspector reviews the electrical plan at the site on the day, with the permit card there and the maker's installation instructions on hand. Its page says "Installers must provide evidence that equipment is appropriately listed/labeled" to the UL standards that apply. Ask the installer to bring it.
In San Diego, the PV inspection guidelines, an undated document on the city's site, list a rough electrical inspection for concealed wiring and array bonding and grounding, then a final of the complete system. A CAL-OSHA compliant ladder must be secured in place. Where a separate utility disconnect is required, an SDG&E approval letter has to be on site.
From the final inspection to permission to operate
The city signs off first. SDG&E's NEM application says the city or county inspector's final approval is required before SDG&E does its own field inspection, and that the inspector notifies SDG&E's New Service Department directly. Its Net Metering Team can't accept copies of an electrical permit. San Diego's 2017 edition of Information Bulletin 301 said the system "is not approved to energize until SDG&E approval is obtained."
SCE issues permission to operate once a project gets final approval, and it says most standard projects get it within 10 business days of a completed package. Non-standard projects can take longer. PG&E's interconnections page, written for projects moved to the Solar Billing Plan, says the agreement has to be signed and any outstanding inspection documents submitted before PTO. SDG&E's pages don't print a residential permission-to-operate timeline, so ask the installer when it expects SDG&E's letter.
Bring the contract with its cover-page disclosure (B&P 7169), which shows the total cost including financing, and the start and completion dates the contract had to state. Add the permit record and the utility's permission-to-operate letter. Customers on NEM 2.0 may stay on that tariff for 20 years from the date they interconnected, and NBT customers keep theirs nine years, so the letter is worth keeping with the report.
What each finding in a written report can be measured against
Ask the inspector to name the rule or document each finding is measured against. For roof layout, the 2022 California Residential Code R324.6 calls for two pathways at least 36 inches wide on separate roof planes, with an 18-inch ridge setback when the array covers 33 percent or less of the plan-view roof area and 36 inches above that. R324.6 exempts roofs with a slope of 2:12 or less. The 2025 code took effect January 1, 2026 and may differ, so ask which edition the report uses.
For equipment, ask for make and model so you can compare them with the CEC's solar equipment lists. The CEC says listing isn't a statewide installation requirement, though some utilities or local governments may ask for it. For production, ask for the system size in kW DC and the tool behind any annual production estimate.
An inspection when you buy or sell a home with solar
If the system is leased or on a power purchase agreement, you don't own it, and CSLB's supporting-information form asks whether the contract can transfer to a new homeowner. Revenue and Taxation Code 73 keeps a new active solar system out of reassessment only if it was completed before January 1, 2027, and those systems stay excluded until a change in ownership. Ask the seller for the completion date and the permit record, and the solar and home sale guide covers the rest of the paperwork.
For a sale, B&P 7195, a statute that doesn't mention solar, defines a home inspection as "a noninvasive, physical examination, performed for a fee in connection with a transfer" of a home of one to four units. It covers the mechanical, electrical and plumbing systems and the structural components. Section 7196 holds a home inspector who isn't a general contractor, an architect, a registered engineer or one of the other professions it names to the care "a reasonably prudent home inspector would exercise." Ask whether the array is in scope.
When an inspection finding can't wait
- Call 911 for smoke, a burning smell or fire coming from the inverter, panels or wiring, and stay clear of them.
- The monitoring app shows lower production than you expected.
- The app is offline.
- One panel looks cracked, with no smoke or burning smell.
What to gather from the ground and the app
- Find the contract, the disclosure page and the warranty papers.
- Locate the permit record and the utility's permission-to-operate letter.
- Screenshot the monitoring app's output history, and note any error message exactly as shown.
Inspections that come with the permit
The city's inspection is tied to its permit, and our model adds no permit fee to a private inspection. If an inspector recommends work, ask the building department whether the work needs a permit; the interconnection and permits page covers the utility side.
Ask for the company's contractor license number and look it up with your state's licensing board before you sign.
Questions people ask
Does the city inspection replace a private inspection?
They are different visits. The city inspects as part of the permit, the utility gives permission to operate, and a private inspection is one you order. Long Beach, for one, says its express permit fees cover all required inspections.
What rule is the roof layout measured against?
The 2022 California Residential Code R324.6 sets pathways and ridge setbacks. The 2025 code took effect January 1, 2026 and may differ, so ask which edition applies.
Do inspectors check the CEC equipment lists?
The CEC says listing is not a statewide installation requirement. Some utilities or local governments may require it, so ask your inspector what it compares.
What should I have when I sell a house with solar?
The contract, the permit record, the permission-to-operate letter and the completion date. If the system is leased, the contract decides whether it transfers to the buyer.
How much does a solar inspection cost in California?
The model puts a visit at $165 to $355 per inspection visit; that is an estimate, not a quote. City permit inspection rows are separate and are shown in the table.
- U.S. Bureau of Labor Statistics, OEWS May 2025: Solar photovoltaic installers (SOC 47-2231), California statewide, mean hourly wage Read Oct 23, 2026.
- U.S. Bureau of Labor Statistics, OEWS May 2025: Solar photovoltaic installers (SOC 47-2231), United States (national), mean hourly wage Read Oct 23, 2026.
- SolarPanelMatch: how we estimate costs, California (editorial policy) Read Oct 23, 2026.
- BLS Public Data API (OEWS series OEUS060000000000047223101..13, OEUN000000000000047223101..13) Read Oct 23, 2026.
- Solar permit fee, Visalia Read Oct 23, 2026.
- Solar permit fee, San Diego Read Oct 23, 2026. Confirm with the source before you rely on it.
- Solar permit fee, San Francisco Read Oct 23, 2026. Confirm with the source before you rely on it.
- Solar permit fee, Long Beach Read Oct 23, 2026.
- CPUC Electric Rule 21: Generating Facility Interconnections Read Oct 23, 2026.
- 2022 California Residential Code, Title 24, Part 2.5, R324.6 (ICC Digital Codes) Read Oct 23, 2026.
- CEC Solar Equipment Lists Program Read Oct 23, 2026.
- B&P Code 7169 (leginfo) Read Oct 23, 2026.
- CSLB bulletin 20-22, solar contracts Read Oct 23, 2026.
- CPUC Net Energy Metering and Net Billing Read Oct 23, 2026.
- CSLB Solar Energy System Supporting Information Read Oct 23, 2026.
- Revenue and Taxation Code 73 (leginfo); BOE LTA 2024/031 Read Oct 23, 2026.
- City solar permit page, Simi Valley Read Oct 23, 2026.
- Solar permit fee, Oakland Read Oct 23, 2026. Confirm with the source before you rely on it.
- City solar permit page, Thousand Oaks Read Oct 23, 2026.
- City of Long Beach, Solar Photovoltaic (PV) Process Read Oct 23, 2026.
- City of San Diego, PV Inspection Guidelines (legacy PDF) Read Oct 23, 2026. Confirm with the source before you rely on it.
- City of San Diego, Information Bulletin 301 (July 2017 PDF) Read Oct 23, 2026. Confirm with the source before you rely on it.
- City of San Jose, Solar & Storage Battery Projects Read Oct 23, 2026.
- SCE, Net Energy Metering FAQ Read Oct 23, 2026.
- SDG&E, Net Energy Metering application, Form 142-02773 Read Oct 23, 2026.
- PG&E, Interconnections & Renewables Read Oct 23, 2026.
- California Legislative Information, B&P Code 7195 (Wayback copy 2025-08-19) and 7196 (live) Read Oct 23, 2026. Confirm with the source before you rely on it.