Westland particulars
Westland charges solar by the panel on its electrical permit application, revised July 1, 2026. It lists item 24, a photovoltaic system "where the total inverter generating capacity is less than 5,000KW," at $10.00 each panel, and item 25, capacity "no less than 5,000KW," at $15.00 each panel. The row wording follows the state form, but the state form's amounts for the same rows are $2 and $1. Ask the Building Division (734-467-3210, per the city's page) which row applies to your system and what it's charging per panel today.
Westland shows up as DTE Electric territory on the MPSC map, and your address check with DTE (800-477-4747) is the final word. The Building Division sits in the Planning and Building Department and issues the city's electrical permits. The Michigan Public Service Commission's consumer tips say to get at least three bids and to ask each company about insurance, years in business, warranties and three customer referrals. With a per-panel permit, each bid should state its panel count. Multiply that count by the rate the Division confirms, and check that each bid's permit line matches.
Interconnection and permits in Westland: what to know
The Building Division, at 734-467-3210 on the city's page, issues the city's electrical permits. LARA's schedule with $2 and $1 is the state's own, and Michigan cities charge their own fees.
DTE, Westland's utility on the state's map (confirm it for your address), charges $50 for a Level 1 or 2 application, and the installer has 180 days after DTE's approval to upload the inspection sticker.
Permits for interconnection and permits in Westland
The state electrical permit application asks for the contractor's Michigan license number, so the permit is pulled under it.
When to call 911 and when it can wait
- Smoke, a burning smell or fire at the inverter, panels or wiring is a 911 call. Leave the equipment alone.
- An application the utility hasn't answered yet.
- A permit sheet you haven't been able to find.
What to settle before the paperwork starts
Try this first: ask the Building Division which class applies to your system and whether the printed per-panel rate has changed.
- Ask who files the utility application and who pulls the city permit.
- Ask your building department for its current solar sheet and whether a building permit is also needed.
- Ask the company which of these fees its price includes.
- Look up its electrical contractor license number with LARA.
- Ask for the utility's approval to operate in writing before the final payment.
What interconnection and permits cost
The estimate below is the Michigan-wide one, adjusted for Michigan wages and not for Westland in particular. The same table is on the interconnection and permits page. How we estimate costs. Prices as of Oct 23, 2026.
| Item | Figure | What it is |
|---|---|---|
| DTE Rider 18 application, Level 1 and 2 | $50 | DTE's interconnection procedures dated July 1, 2026. Study or construction fees may apply if triggered. |
| Consumers Energy distributed generation application review, Levels 1 to 3 | $50 | Consumers' interconnection cost table. Supplemental review, system impact and facilities study are listed at $0. |
| Solar photovoltaic electrical permit, Detroit | $278 per inverter connection per visit (grid-connected); $165 per visit (no grid) | BSEED fee schedule effective January 1, 2024. A subsequent installation inspection visit is $176 each. |
| Electrical permit, alternative power, Grand Rapids | $42.00 for the first 10 kW, then $4.00 per added kW | FY2027 fee schedule, electrical. |
| Electrical permit, solar per kW, Royal Oak | $20.00 per kW | Master fee schedule effective July 1, 2025. |
| Electrical permit, alternative power, Wyoming | $40.00 for the system and first 10 kW, then $4.00 per added kW | Fee schedule effective 2026. The electrical application fee is $50.00 and includes one inspection. |
| Electrical permit, solar panels, Taylor | $19.00 per panel, plus a $50.00 application fee | 2025-2026 schedule. |
| Electrical permit, per PV module up to 20 kW, Kalamazoo | $7.00 per module, plus an $83.00 application fee | 2026 application. Residential PV also needs a building permit. |
| Expedited residential solar electrical permit, Ann Arbor | $0 for line-item solar fees | The city's 2020 checklist and fee sheet say it doesn't charge for them; an inspection is $35.00 if applicable. The city may have changed fees since. |
| Electrical permit, solar panel modules, East Lansing | $12 per module | City electrical permit fees, undated. The building side is separate: a $60 solar permit application fee, and $140 for systems under 10 kW covering the application and rough and final inspections. |
| Electrical permit, alternative energy up to 50 kW, Battle Creek | $50.00 | Schedule effective July 1, 2026. Per-panel rows of $2.00 and $1.00 are also printed; ask the city whether both apply. |
| State electrical permit schedule, solar photovoltaic system | $75.00 application, then $2.00 or $1.00 per panel | LARA's state form applies only where the state inspects, and its column layout is ambiguous. |
These rows are fees that utilities and cities publish, each with the date or fiscal year of the schedule. None is an installer's price, and the estimate model has no row for this service. Full method.
Questions about interconnection and permits
How long does DTE take to approve a solar system?
DTE says the process takes approximately six weeks. It has 10 business days to say whether an application is complete, and you have 60 business days to fix deficiencies.
How much does a solar permit cost in Michigan?
There's no statewide figure, because each city sets its own fee. The cities we cite run from $0 in Ann Arbor, on a 2020 sheet, to $278 per inverter connection per visit in Detroit.
Does Michigan require a building permit for solar too?
Many cities do, including Dearborn, Kalamazoo and East Lansing. Ask your building department what it needs.